Crown Valley Park Improvement Project, Tier III

The Crown Valley Park Improvement Project Tier III includes a 30,000-square foot Crown Valley Park Community Building with staff offices and rooms available to rent by the public for special events. The three-story building will have a contemporary look and features a dedicated art room, fitness and dance room, collaborative tech room, multi-purpose room with a 300-person dining capacity and a catering kitchen, and multi-purpose classrooms. The lower aquatics level features locker rooms with private changing areas and classrooms that open to the pool deck. The upper level will feature an outdoor rooftop patio overlooking the pool.

The City expects to begin construction of the new Community Center on August 13, 2018, with the goal of completing the final phase of the project in early 2020.

Community Building
Community Building Pool

Crown Valley Park Community Building Construction Activity Timeline:

  • July 31, 10 am – Groundbreaking Ceremony (amphitheater).
  • August 1 and August 3, 6 am - Staff offices/Registration office trailer delivery to the softball field area at CVP.
  • August 1 through September 30 –Trail work on the portion between the bridge entrance and the YMCA.  
  • August 11, 11 am-1 pm – Open House at the soon-to-be-demolished Community Center. Patrons can view renderings, talk to staff about closures, eat pizza and sign the walls in the building.
  • August 12 – Last day of service at the pool, Sprayground, playground and amphitheater.
  • August 13 through August 17 – Staff relocation to new offices. During this week, the phones and computers at CVP will be down. Patrons wanting to register for classes, questions, etc will be referred to staff at Sea Country Senior and Community Center.
  • August 13  – Official Start of Construction.
  • August 20 – Reopen Registration office to the public in the modular building at CVP.
  • Feb. 2019 – Pool reopens in limited capacity (tentative).  The possible reopening of the playground (and Sprayground in the summer months) will be continually assessed, pending available parking and construction activity impacts.  
  • Spring 2020 – Community Building Grand Opening.