Crown Valley Park Tier 2 Entry Improvements

Arch Small.jpg

 
August 8, 2017 marks the completion of Tier II Park improvements at Crown Valley Park.  On this momentous day, over 100 people celebrated the second of three major renovation phases and saw the City’s investment in making this Park an attractive and inviting place for community members and future generations to enjoy for years to come!  

Completed improvements included a new culvert crossing that replaced a previous dip crossing. This means the Park entry does not need to be closed anymore due to flooding during heavy rainstorms.  The bridge also features decorative lighting, along with sidewalks and bike lanes on each side to enhance pedestrian safety and access to the Park. A new decorative and branded metal archway was added across the entryway to highlight the entrance to the Park. In addition, a digital electronic marquee was installed at the Park entrance to promote City events and recreation programs.

The celebration also marked the completion of two new parking lots with convenient access from Crown Valley Parkway, adding approximately 66 parking spaces for visitors. The north lot is accessible from the Park entry road, and will be convenient for softball and lower soccer field users. The south lot has direct access from Crown Valley Parkway and will be convenient for upper soccer field and trail users. A new staircase will also provide direct access to the upper soccer field. Restoration of the creek, water quality improvements, and the conversion of the Niguel Botanical Preserve from potable to reclaimed water rounded out Tier II improvements.

The next phase, Tier III of the Improvement Project, will include a 30,000-square foot Crown Valley Park Community Center with staff offices and rooms that the public will be able to rent for their special events. The three-story building will have a contemporary look and feature a dedicated art room, fitness and dance room, collaborative tech room, multi-purpose room with a 300-person dining capacity and catering kitchen, and multi-purpose classrooms. The lower aquatics level features locker rooms with private changing areas and classrooms that open to the pool deck. The upper level will feature an outdoor rooftop patio overlooking the pool. 
A festival plaza and other pedestrian-oriented amenities are also in the planning phases, as well as a realignment of the main drive aisle and parking next to the new building. There will also be some modest exterior improvements to the City-owned YMCA building. 

The City expects to begin construction of the new Community Center in late summer 2018, with the goal of completing the final phase of the project in early 2020. 


Project Location:   Crown Valley Park

Contractor: Los Angeles Engineering, Inc.

Construction Dates: July 5, 2016 to
                                                 August 2017

Construction Cost: $8,736,169

City Contact: Ziad Mazboudi


CVP Tier 2 Time Lapse video

Watch weeks 38 through 55 video

Watch weeks 1 through 38 video
 
    
 Week Date Update Video

57

August 11, 2017
Update


Video
 
56 August 4, 2017
Update

 
55 July 28, 2017
Update

 Video
54
July 21, 2017

Update  
53
July 14, 2017

Update  
52
July 7, 2017

Update  
51 June 30, 2017
Update

 Video
50 June 23, 2017
Update

 
49 June 16, 2017  
Update

 
48  June 9, 2017  
Update

 
47 June 2, 2017
Update
 
 
46 May 26, 2017  
Update

Video 
45 May 19, 2017
Update
 
 
44 May 12, 2017
Update
 
 
43 May 5, 2017 
Update

 
42 April 28, 2017 
Update

  
 Video
41 April 21, 2017 
Update

 
 
40 April 14, 2017 
Update

 
 
39 April 7, 2017 
Update

 
 
38 March 31, 2017   
Update

 
 Video
37 March 24, 2017 
Update

 
 
 
36

March 17, 2017  Update   
 
35

March 10, 2017  Update   
 
34

March 3, 2017  Update   

33
 
February 24, 2017  Update  Video

32

February 17, 2017 Update   
31 February 10, 2017  
Update

 
30 February 3, 2017 
Update
 
 
29 January 27, 2017 
Update
 
 Video
28 January 20, 2017 
Update
 
 
27 January 13, 2017 
Update
 
 
26 January 6, 2017 
Update
 
 
25 December 23, 2016
Update
 
Video 
24 December 16, 2016
Update
 
 
23 December 9, 2016
Update
 
 

22
December 2, 2016  Update  
 
21
November 25, 2016  Update Video 
 
20
November 18, 2016  Update  
19

November 11, 2016

Update

 

18

November 4, 2016

Update



17
October 28, 2016 Update  Video
16
October 21, 2016  Update  

15 October 14, 2016
Update

 

14

October  7, 2016

Update

 

 13

 September 30, 2016

 Update

 Video

 12

 September 23, 2016

 Update

 

 11

 September 16, 2016

 Update

 

 10

 September 9, 2016

 Update

 

 9

 September 2, 2016

 Update

 

 8

 August 26, 2016

 Update

Video 

 7

 August 19, 2016

 Update

 

 6

 August 12, 2016

 Update

 

 5

 August 5, 2016

 Update

 

 4

 July 29, 2016

 Update

 Video

 3

 July 22, 2016

 Update

 

 2

 July 15, 2016

 Update

 

 1

July 8, 2016

 Update

 



             







Contact