Sidewalk Improvement Program


sidewalk 1


Project Description:

The Sidewalk Improvement Program will perform routine maintenance and repairs to the City's sidewalks on an annual basis. Improvements include repair and replacement of damaged sidewalk panels and replacement of curb ramps to meet ADA requirements. 

Project Delivery Schedule:

  • Design Completed: October 2023
  • Start Construction: January 2024
  • Construction Complete: May 2024
  • Current Phase: Bidding Phase 
  • Current Status: Bidding is 50% complete
CIP - Sidewalk Improvement Program


Project Funding:

  • FY 23-24 Project Budget: $250,000 (CDBG/Gas Tax (SB1)